Huntington Middle School: The Next Chapter
The proud history of Huntington High School and Huntington Middle School will continue with the construction of a new 600-student middle school, anticipated to open during the 2026-2027 school year.
The new middle school is part of the city’s Southeast Community Resource Area that is set to include a public library and community center, as well as sports and recreation features.
Construction Progress Update
July 16, 2025
The Huntington Middle School building site is divided into four (4) building zones, A, B, C, and D. MEB General Contractors, Inc, the Contractor, is developing the building pad in the order of zones C, D, B, and A. The work completed in these building zones are as follows:

Zone "C"
- All remaining structural steel, joist, and deck was completed on July 11.
- Slab on grade 100% including polished concrete areas.
- Begin overhead mechanical, plumbing, & electrical rough-in gym and locker room areas.
- Metal stud framing at gym exterior (parapets and overhang) scheduled to begin July 21.
- Interior "non" load bearing walls in locker room 25% complete.
Zone "D"
- Structural steel, joist, and deck in kitchen/cafeteria area 75% complete.
- Structural steel, joist, and deck are scheduled to be complete by the end of July.
- All 1st floor areas with polished concrete floors have been placed.
- Main Mechanical and Electrical room slabs have been placed.
Zone "B"
- All 1st floor areas with polished concrete floors have been placed.
- Structural steel erection began on July 14 starting in the classroom wing.
Zone "A"
- All areas with polished concrete floors have been placed.
Field House
- Structural slabs are 100% complete.
Utilities
- Street closure(s) occurred along 35 Street between the intersections at Orcutt and Wickham Avenues for storm water structure installations.
Overall Completion
- Overall Completion is 25% complete.
- Milestone Date: June 24, 2025 - 1st floor building footprint is on a concrete slab / building out-of-ground.
Huntington Construction Project
Architect: Quinn Evans
Contractor: MEB General Contractors
Projected Timeline:
-
March 1, 2024
Advertise Project -
April 12, 2024
Bid Opening -
May 20, 2024
Notice of Intent to Award -
August 22, 2024
Building Permit for Construction -
September 5, 2024
Groundbreaking Ceremony, 9 a.m. -
February 3, 2026
Substantial Completion -
April 5, 2026
School Site and Building Completion -
June 4, 2026
Final Completion
More Information
Construction Progress Report Archive
- July 2025 Construction Update
- June 2025 Construction Update
- May 2025 Construction Update
- April 2025 Construction Update
- March 2025 Construction Update
- February 2025 Construction Update
- January 2025 Construction Update
- December 2024 Construction Update
- November 2024 Construction Update
- October 2024 Construction Update